|
Preparation to Blast Cleaning for Cement Mortar
Lining :
Prior to blast cleaning, the each pipe shall be
inspected by the followings;
-
Pipe
identification control
-
Pipe shall be
accepted as PE coated pipe condition
-
The internal
surface control
-
The pipe
internal surface shall be inspected and cleaned to remove all
traces of oil, grease and loose deposits. Any visible trace of
oil or grease shall be removed using an appropriate non-oily and
non-toxic product.
-
If pipes have
been in contact with marine or industrial atmosphere, they shall
be cleaned before abrasive blasting to remove any contamination.
Cleaning shall be carried out using an adapted process.
Surface Preparation :
The pipe surface shall be grit/shot blasted to ensure
the SA 2 1/2 degree of cleanliness.
The finished pipe surface shall be completely removed
all traces of rust and shall be provided a surface average roughness
(RZ) of 50 to 100 microns.
Pipes shall be heated to remove any surface moisture
and to ensure more than 3ºC
above the ambient dew point.
The ambient relative humidity shall not exceed 85 %
as measured using a hydrometer and digital thermometer.
Immediately after abrasive blasting, all dust and
traces of abrasives shall be removed from the pipe surface by
brushing and vacuum cleaning.
Each cleaned pipe shall be inspected for surface
defects. Any defect shall be removed.
Ambient Control :
The ambient temperature and ambient relative humidity
shall be measured using
a hydrometer and digital thermometer.
The ambient relative humidity and ambient temperature
shall be recorded to the shift report.
The grit-blasting is not permitted when the ambient
relative humidity exceeds 85 %.
The metal temperature shall be 3ºC
above the ambient dew point temperature.
Any pipe which has not been coated before degradation
of its surface preparation shall be completely re-blasted before
coating.
Surface Test and Inspection :
The below tests and inspections shall be performed on
blast cleaned pipe:
Two methods can be used in measuring surface
roughness measurements.
Method 1- By visual comparison
gauge,
Method 2- By a digital profile
measuring device.
Standard grid and shot comparator is compared
to the pipe surface. The coinciding segment of the comparator shall
be decided.
Surface roughness measured by a digital profile measurement device.
Surface roughness shall comply with Rz=50-100
µm
The calibration of equipment shall be performed by reference blocks.
-
Surface cleaning
degree :
Standard comparison pictures are used to decide the
degree of the surface cleanliness. Surface quality degree shall be
Sa
2 ½
Residual dust shall comply with acceptable categories
of ISO 8502-3 and Specification.
The surface defects which appearance effect of
grit-blasting or other reason shall be checked by visual inspection.
In case of any grinding or mechanical reworks, the wall thickness
shall be ultrasonically examined and remaining wall thickness shall
be met minimum specified requirements.
Pipe external surface shall be cleaned of all dust
and foreign matter using clean dry compressed air or vacuum
cleaning. Residual dust shall comply with categories of ISO 8502-3
and specification.
Coating Application
Cement Mortar shall be composed of cement, sand and water well mixed
and of proper consistency to obtain a dense, homogeneous lining that
will adhere firmly to the pipe surface. Cement Mortar for lining
shall consist of one part cement to not more than three parts fine
aggregate by weight. Excessive amounts of batch mix water shall be
avoided. Only enough water to obtain proper placement
characteristics of the batched cement mortar shall be used. The
water-soluble chloride-ion content of the cement-mortar lining mix,
expressed as a percentage of the weight of cement shall not exceed
0.15 percent.
Mixing:
The
cement Mortar shall be mixed in batches. The amount of cement and
sand entering into each batch shall be measured by weight. The
quantity of water entering the mixer shall be measured automatically
by an adjustable device, or it shall be otherwise measured to ensure
that the correct quantity of water is being added.
Condition during application:
The temperature of the substrate should be minimum 15°C and at least
3°C above the dew point of the air.
There
is Centrifugal Process methods of lining.
The
necessary amount of mortar for obtaining the required lining
thickness is poured by boom-nozzle system along the pipe.
The
boom is moved with constant speed inside the pipe from one end to
the other end to provide evenly distribution of the mortar.
Then
the pipe is rotated.
The
mortar is spread around internal pipe surface under centrifugal
force. The mortar is compacted and residual water is drained at the
end of the rotation.
Cement-Mortar Curing
Immediately after completion of spinning, the pipe sections may be
moved to a curing area. Care shall be exercised at all times to
prevent damage to the lining.
At
the option of the manufacturer, linings shall be accelerated cured,
moist cured, or cured by a combination of accelerated and moist
curing.
Accelerated curing or moist curing may be used interchangeably on a
time-ratio basis of 5 1/3 h of moist curing to 1 h of accelerated
curing. In any case, the total curing period shall be equivalent to
96 h of moist cure and minimum curing period before applying the
exterior coating shall be equivalent to 24 h of moist cure.
The
lining shall be kept continually moist until completion of the
minimum specified curing period.
Moist
Curing may be used only if the minimum ambient temperature exceeds
5ºC continuously during the required minimum curing period. No
credit shall be allowed for any time during which the temperature
drops below 10ºC.
On
arrival at the curing area, but not later than 30 min after
completion after lining operation, pipe ends shall be covered with
plastic cap. If a cement-mortar exterior coating is not specified,
the lining shall be moist cured for 96 h before shipment.
After
curing, the water shall be sprayed on the lining and wetting on the
surface for seven days.
Defective Lining :
General:
All
defects, including, but not restricted to, sand pockets voids, over
sanded areas, blisters and cracking as a result of impacts, shall be
cut out and replaced by hand or pneumatic placement to the same
thickness as required for the cement mortar lining
Lining Cracks:
Temperature and shrinkage cracks in the cement mortar lining less
than 1,6 mm in width need not be repaired. Cracks wider than 1.6 mm
need not be repaired if it can be demonstrated to the satisfaction
of the purchaser that the cracks will be heal autogenously under
continuous soaking in water. The autogenous healing process may be
demonstrated by any procedure that keeps the lining of the pipe
continually wet or moist. Pipe used in the demonstration shall be
representative of the pipe to be supplied and water for the
moistening of the pipe shall be chemically similar to the water to
be carried in the pipeline.
Cement Mortar Lining Thickness :
|
Nominal Pipe Size |
Lining Thickness |
Tolerance |
|
inch |
mm |
inch |
mm |
inch |
mm |
|
4-10 |
100-250 |
¼ |
6 |
-1/16, +1/8 |
-1.6, +3.2 |
|
11-23 |
280-580 |
5/16 |
8 |
-1/16, +1/8 |
-1.6, +3.2 |
|
24-36 |
600-900 |
3/8 |
10 |
-1/16, +1/8 |
-1.6, +3.2 |
|
>36 |
>900 |
½ |
13 |
-1/16, +3/16 |
-1.6, +4.8 |
Cement Mortar Coating Test :
Surface Cleanliness Comparison
Surface Profile (Roughness)
Sand-Sieve Analysis
Lining Thickness Measurement
Curing
Visual Check
|